Managing Director & CEO's Report
This year has been one of major transformation for Kingsgate during
which our asset portfolio has been greatly enhanced. The merger with
Dominion added a second gold mining operation at Challenger in South
Australia and the takeover of Laguna Resources NL delivered a 70%
interest in the Nueva Esperanza (formerly Arqueros) advanced silver/
gold project in the highly prospective Maricunga gold belt in central
Chile. The major plant expansion at Chatree has progressed through to
completion during the year with commissioning in October. Pleasingly,
this expansion has remained on schedule and is likely to be more
than 5% below the US$100 million EPCM contract amount that is an
exceptional result considering the unusually heavy wet season this year
and the pressure on major capital resource projects around the world.
Laguna subsequently acquired two strategic lease areas, Esperanza
and Chimberos, which surround and enhance the overall project area
and delivered an additional 20 million ounces of silver resources, major
infrastructure and considerable surface rights. The combined project
area is now known as Nueva Esperanza. The feasibility study for the
project is well underway and expected to be completed early in 2012.
The acquisition of the Bowdens silver project near Mudgee in New
South Wales complements Kingsgate’s current growth pipeline.
Kingsgate has commenced a feasibility study that builds on the high
quality work previously completed by Silver Standard Inc. A detailed
exploration programme will be undertaken over the next few months
to defi ne the full extent of the mineralisation. The feasibility and
resource development work is expected to lead to a decision to mine
towards the end of 2012.
This past year has set the platform for signifi cant growth in production,
cash fl ow and earnings over the next three years and continues to
support Kingsgate as a proven value creator.
Operations
Chatree
Chatree mine produced 76,248 ounces during the year. The decrease
in gold production is largely due to mining and processing of lower
grade ore while approval to access C North, where higher grade ore was
scheduled to be mined during the June half of the year, was delayed.
Mining was also impacted by restrictions imposed by a night time
operating curfew during the March and June quarters. This resulted in
a lack of fl exibility to access alternative high grade and less intrusive
areas. These restrictions have subsequently been lifted. The heaviest wet
season in a generation has had an impact on operating activities with
major fl ooding disrupting most of Thailand. |
Mining commenced at C North late in the June quarter and it is
expected that high grade ore will be accessed in the December 2011
quarter once the laterite and clay overburden layers have been removed.
The Chatree North Expansion project is being constructed as a separate
2.7 million tonnes per annum (Mtpa) ore processing plant located
besides the current 2.3 Mtpa Chatree processing plant. This will result
in a combined total ore processing capacity of 5 Mtpa. Construction
is on schedule for commissioning in October 2011 and the project is
coming in around 5% under the original US$100 million budget. This is
a signifi cant result in particular given the excessive rainfall over the past
12 months in Thailand.
In addition, the construction programme with over 1.2 million man
hours has progressed without a Lost Time Incident.
Challenger
The Challenger mine produced 36,886 ounces for fi ve the months since
ownership transferred to Kingsgate.
Production was lower than expected due primarily to the effects of
unusually heavy rainfall during February and March. This prevented
continuous road access with supplies of fuel, consumables and maintenance
parts only intermittently delivered to the site. These disruptions
resulted in low grade stockpiled ore supplementing scheduled higher
grade underground ore leading to lower than planned production. In
the June quarter, the mining operation was also impacted by both mine
grade dilution and production rate caused by pillar failures in a number
of stopes.
A new high grade shoot at Challenger West will be developed during the
forthcoming year contributing to the total gold production expected to
exceed 100,000 ounces. |